| Course | NR 711 Fiscal Analysis and Project Management |
|---|---|
| Week | 7 |
| Paper type | Risk register |
| Length | About 1,140 words, 5 pages |
| Format | APA 7 student paper |
| School | Chamberlain University |
| Program | MSN, Nurse Executive |
| Updated | October 2026 |
Free sample paper for NR 711 Week 7
Risk Register for the Video Patient Monitoring Project on 4 West, Priced and Ranked by Expected Cost
Student Name
College of Nursing, Chamberlain University
NR 711: Fiscal Analysis and Project Management
Instructor Name
Month Day, Year
Risk Register for the Video Patient Monitoring Project on 4 West, Priced and Ranked by Expected Cost
How the Register Works
The register below holds nine risks for the video monitoring project on 4 West, from purchase through the first year of operation. Nine is deliberate. A register with forty rows is not read weekly, and a risk nobody reads about cannot be caught early. Each row gives the event in one specific clause, a likelihood band, a dollar exposure, the expected cost, an owner by role and a response with its own price and date.
Likelihood is expressed in three bands rather than decimals, because the inputs are judgments, and multiplying a guess to two decimal places only makes it look measured. Low means about one chance in ten over the period; medium means about three in ten; high means about six in ten. The expected cost multiplies the band's midpoint by the exposure and is rounded to the nearest $10. Rows are sorted by expected cost, so a quiet, expensive risk sits above a dramatic, cheap one (International Organization for Standardization, 2018).
The Register
Table 1
Risk Register, Video Monitoring on 4 West
| Rank | Event | Likelihood | Exposure | Expected cost | Owner | Response, cost and date |
|---|---|---|---|---|---|---|
| 1 | Nurses keep ordering in-person sitters for camera-eligible patients in the first quarter | High | $45,500 | $27,300 | Nurse manager, 4 West | Charge nurse reviews every sitter order each morning for 90 days; about $1,370 in nurse time; from go-live |
| 2 | 5 West leaves the shared technician arrangement | Low | $105,120 | $10,510 | Director of nursing, medical-surgical services | Two-year participation agreement signed by both directors; $0; by 30 April 2027 |
| 3 | Walls in some rooms have no conduit path, forcing surface raceway | High | $6,000 | $3,600 | Facilities project manager | Open-wall survey of all 32 rooms before the purchase order; $650; by 15 May 2027 |
| 4 | Weekend charge nurse vacancy stops the morning sitter review | Medium | $11,000 | $3,300 | Director of nursing, medical-surgical services | House supervisor named as backup reviewer in policy; $0; by go-live |
| 5 | Go-live slips a month while the license and technician are already paid | Medium | $9,960 | $2,990 | Director of clinical engineering | License and technician start tied to go-live in contract and offer letters; $0; by contract signature |
| 6 | Patients or families decline cameras more often than the 20% planned | Medium | $9,000 | $2,700 | Unit educator | Scripted consent conversation in English and Spanish; $480 for translation; by 15 June 2027 |
| 7 | A camera loses signal unnoticed and an unobserved patient falls with injury | Low | $14,000 | $1,400 | Monitor technician lead | Loss-of-signal alarm configured and tested weekly; $0 beyond the configuration fee; from go-live |
| 8 | Signal dropouts in week one extend parallel running by 14 days | Medium | $4,032 | $1,210 | Network team lead | Wireless signal survey of all 32 rooms; $1,200; by 1 June 2027 |
| 9 | Camera batteries fail before month 18 | Medium | $2,160 | $650 | Clinical engineering technician | Monthly battery health report from the vendor portal; $0; from go-live |
Note. Note. Expected cost = band midpoint (10%, 30% or 60%) times exposure, rounded to $10. Totals: exposure $206,772; expected cost $53,660; response cost $3,700.
Reading the Top of the Register
The largest expected cost has nothing to do with the cameras. It is the risk that nurses go on ordering in-person sitters out of habit, which would leave the program paying for cameras and sitters at the same time. Its exposure is a quarter of the first year's expected sitter savings, about $45,500, and the likelihood is high, because changing an ordering habit on a unit with 58 nurses rarely happens in the first month. Programs that reduced sitter use did it with a review protocol that someone ran daily, not with technology alone (Burtson & Vento, 2015). The response costs about $1,370 in charge nurse time and is the best value in the register.
The second row is unlikely but would be expensive. If 5 West withdrew from the shared technician, 4 West would carry the full $210,240 a year, and its half share of $105,120 would become a new cost. A signed agreement costs nothing and removes most of the risk.
Responses That Cost About What They Save
One response is flagged on purpose. The wireless survey in row 8 costs $1,200 to remove an expected cost of $1,210, so on money alone it is close to even. It is kept for a reason the money does not show: a camera that drops out is an unobserved patient, which is the event in row 7. A response priced at about what it saves should be chosen for a stated reason, not by default.
Row 4, the weekend review, has no price because the backup is a house supervisor already on duty. It is still written as an action with a date, because a response written as an intention to monitor tends not to happen.
Exposure Against the Reserve
The project's contingency reserve is $4,800 and can pay only for capital items inside the scope. Of the nine rows, only row 3 is a capital risk, with an exposure of $6,000 and an expected cost of $3,600. The reserve covers the expected cost but not the full exposure: if the full exposure arrives, the overrun could exceed the reserve by about $1,200. This is reported now so the sponsor can decide in advance whether to raise the reserve or accept that an overrun would go to the capital overrun account.
The other eight rows are operating risks, with a combined expected cost of $50,060, and no reserve covers them. They fall on the program's net return, which the business case put at $67,030 over three years. That margin absorbs the expected cost of the operating risks once but not twice, which is why the response in row 1 matters more than any other line here (Project Management Institute, 2021).
How the Register Is Used
The nurse manager reviews the register every Monday in the first 90 days and monthly after that. A row closes when its trigger can no longer occur: row 3 closes when the open-wall survey is done, row 5 at go-live. A new row is added only with every column filled. The fall exposure in row 7 uses the hospital finance office's estimate of the added cost of a fall with injury, which is in line with published models of fall costs (Spetz et al., 2015).
Totals
The nine exposures total $206,772, the expected costs $53,660 and the responses $3,700. Spending $3,700 now to reduce an expected cost more than fourteen times larger is the case for acting on the register before go-live rather than after.
References
Burtson, P. L., & Vento, L. (2015). Sitter reduction through mobile video monitoring: A nurse-driven sitter protocol and administrative oversight. JONA: The Journal of Nursing Administration, 45(7/8), 363-369. https://doi.org/10.1097/NNA.0000000000000216
International Organization for Standardization. (2018). Risk management: Guidelines (ISO Standard No. 31000:2018).
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.
Spetz, J., Brown, D. S., & Aydin, C. (2015). The economics of preventing hospital falls: Demonstrating ROI through a simple model. JONA: The Journal of Nursing Administration, 45(1), 50-57. https://doi.org/10.1097/NNA.0000000000000154
Reading the NR 711 Week 7 instructions
Keep the register short enough that someone will read it every week; eight to ten rows is usually right. Write each event as one specific clause that has a trigger, not a theme such as staff resistance. Give each row a likelihood band, a dollar exposure if the event happens and an expected cost, and sort the rows by that expected cost. Name an owner by role, not by department. Write every response as an action with its own cost and date rather than an intention to monitor, and flag any response that costs about as much as the risk it removes, with the reason you are keeping it. Under the table, total the exposures, expected costs and response costs, and compare the capital-side exposure with the project reserve. Explain how often the register is reviewed and when a row closes.
How this NR 711 Week 7 example is built
The sample explains its bands first: low, medium and high mean roughly one, three and six chances in ten, and expected cost is the midpoint times exposure, rounded to $10. The table follows with nine rows. Sitter ordering habits rank first; a partner unit leaving the shared technician arrangement ranks second at $10,510; walls without conduit rank third. Other rows cover a weekend review gap, a go-live slip while the license runs, families declining cameras, an unnoticed signal loss, week-one dropouts and early battery failure. The discussion explains why the top row is a behavior, flags the survey whose cost matches its benefit and splits the one capital row from eight operating rows. Totals close the paper: $206,772 exposure, $53,660 expected and $3,700 in responses.
Reading the NR 711 Week 7 grading rubric
A register with no money in it loses the most: a column of events and a column of adjectives cannot be sorted and so cannot be acted on. Nearly as costly is the row so broad it covers everything, such as budget constraints, because there is no trigger to watch and no response that can be priced. Graders then look for responses written as actions with costs and dates, for owners named by role and for a sort order driven by expected cost rather than drama. Points are lost for likelihoods multiplied to two decimal places on inputs that were guesses, for a response costing more than its risk without comment and for total exposure never compared with the project reserve. Registers score well when the top rows clearly drive the project's weekly attention.
Common NR 711 Week 7 mistakes, and how to avoid them
Most first registers list risks well but leave the money out. Send us your project, its budget and reserve and the risks you are worried about, and we can help you write each as a specific event, estimate an exposure, set likelihood bands, price the responses and sort the rows so the important ones rise to the top. We can also help you compare the capital exposure with your reserve. The risks, the estimates and the owners reflect your own project and organization, and the register shows where each figure came from.
Get a NR 711 Week 7 example written to your instructions
Send the register template or column list your classroom uses along with the project it attaches to, and a custom register comes back inside 24-48h with exposures costed and each response owned by a role. The first one is free. Where no template was issued we build the columns a funded project would normally carry.
More NR 711 papers and MSN samples
- NR 711 Week 1: Competing Requests Post
- NR 711 Week 2: Three-Year Cost Analysis
- NR 711 Week 3: Operating Budget Draft
- NR 711 Week 4: Capital Business Case
- NR 711 Week 5: Budget Variance Report
- NR 711 Week 6: Project Scope Statement
- NR 711 Week 8: Funding Recommendation
- NR 703 Week 7: Diagnostic Case Paper
- NR 670 Week 7: Development Plan
- NR 529 Week 7: Retention Plan Built From Leavers
- NR 632 Week 7: Evaluation Report
NR 711 Week 7 questions, answered
How many entries should a register have?
Fewer than feels thorough. Eight to twelve priced entries reviewed regularly beat forty that nobody opens after submission, and sections generally mark the quality of the exposure figures rather than the length of the list. Where your assignment sets a minimum, meet it, and put the weaker entries at the bottom with honest low exposures rather than inflating them.
How do I price a risk I cannot possibly know the cost of?
Build it from two things you can state. A delay costs days multiplied by whatever the project pays per day; a supply shortage costs a quantity multiplied by a substitute price. Put the two inputs in a note beside the figure. Markers accept a rough number with visible working far more readily than a confident one with none.
Does a heat map count as the deliverable?
It counts where your section names it, and then only as a picture of the grid rather than a replacement for it. Colors cannot be totaled, reserved against or handed to an owner. Where a heat map is required, build the priced register first and generate the map from it, so the two never tell different stories.
Where can I find a free NR 711 Week 7 sample paper?
The complete nine-row risk register for a video monitoring project, priced and ranked by expected cost, is shown on this page.
Why does the NR 711 Week 7 register use bands instead of exact probabilities?
The inputs are judgments, and multiplying a guess to two decimal places would make it look measured when it is not, so three coarse bands are used.